Engineering consultants in Pakistan
Loading...
Nationwide - Multiskilled - Multidisciplinary
Engineering Development and Management Consultancy

Water Projects List

Project Client Description Completion
Preparation of Master Plan for Water Supply, Sewerage & Drainage System for Lahore WASA LDA Preparation of specific master plans for water supply, sewerage and drainage sector for Lahore Dist. area, for up to 2040, and develop implementation plans for priority projects. Assess the existing situation of institutional structure of WASA to handle the efficient management of the existing and expanding services needed. Assess the existing infrastructure and propose rehabilitation and expansion, including review of regularity framework. Review the tariff; introduce sound financial management system based on MIS 2017
Feasibility Study for Extension of Water Resources for Faisalabad City- Phase-II Water and Sanitation Agency, (WASA), Faisalabad Design to increase the capacity of the under construction 10 mgd plant to 20 mgd • Design a new treatment 20 mgd plant at a suitable site on the eastern side of the City, and • Design improvement in the arterial network, with necessary additions / modifications • Conducting studies, surveys, investigations • Preparing documents of technical specifications and PC-1 for the project 2017
36” Dia MS Trunk Mains from Hub Treatment Works to Saudabad Pumping Station Karachi Water and Sewerage Board

For the purpose of improving water supply system of Saudabad Malir, KWSB has planned to lay 36” diameter pipeline from Pipri Treatment Works to Saudabad, a dedicated supply system. The present water shortage in the area will be eliminated and water will be equitably distributed around Malir and Saudabad. The project is to be implemented in 14 months. MMP consultants have been appointed by KWSB for detail design and supervision of the project.

2015
Environment and Social Studies, Land Use Plan Including Resettlement Framworks for Thar Coal Fields Coal and Energy Development Department, Government of Sindh Coal-to-Power Development is vital for Pakistan’s present and future power requirements. The discovery of low-ash, low-sulphur lignite coal reserves in the Tharparkar (Thar) Desert in Sindh Province, with estimation of 184.123 billion tonnes has increased both domestic and foreign interests. The area of study is 22,000 sq.km in district Tharparkar and contiguous areas. 2015
Rehabilitation and Strengthening of Water Supply System Under K-III Project Karachi Water & Sewerage Board

Producing an overall existing water supply asset map of 18 towns of Karachi city, covering conveyance and distribution system with particular reference to water trunk mains ranging 33” dia to 72” dia. Leakage detection survey showing previously repaired leaks pin-pointing places where frequent leakages occur. Prepare an aging plan of the transmission and water distribution system to identify such portions of the system where it has completed economic design life and where there are visible signs of deterioration and damage resulting in water loss. Devise the concept of metering in the context to ensure equitable distribution of water and measured flows to the 18 towns of Karachi. Complete detail design and preparation of engineering estimates. Provide specialist services for all contracts with an integrated team of experienced and qualified engineers. Supervision of commissioning & setting to work to the specified standard.

2015
Solid Waste Management Studies of Towns of Central Cluster of Province of Sindh Brisbane City Enterprises Pvt. Ltd. Under Sindh Cities Improvement Program (SCIP) Solid waste generation study including household, commercial, industrial and hospital waste. Solid waste composition study providing necessary inputs for calculating organic and inorganic portions, recyclable materials and combustible waste etc. Data acquisition for time and motion study to find out existing fleet of vehicles, locations of official primary collection points to the existing dumping sites. Also carry out time and motion study for each vehicle which is presently involved in the transportation of solid waste from official primary collection points to the existing dumping sites by giving details of routes and time take for one day. Inventory of existing solid waste management physical infrastructure including assets and staff deployed by the towns, as well as all officially designated and non-designated primary collection points. 2017
Providing/Laying Water Conduction Main from G-13 to I-16 (New Route of Shah Allah Ditta Reservoir) Islamabad – Left Over Work of Phase I & II at Islamabad Capital Development Authority (CDA).

The Consultancy Assignment consists of two phases, The phases and jobs to be carried out are as under: Design Review Reviewed the design of the pipeline with revised route diversions as decided on a holistic basis with specials and fittings positioned adequately. Produced revised detailed construction drawings for portions to be laid or re-Iaid. Reviewed contract documents and provide addendums where necessary, for the existing contractors. Market rate analysis and review of Cost Estimate Top Supervision of the Construction of Conduction Mains Provided Top Supervision for the execution. Witness testing and commissioning. Verified “As Built” Drawings, provided by the Contractor(s) Support the Client in project closing.

2013
Consultancy Services for Mapping, Planning, Feasibility Studies, Detailed Design and Supervision (SCIP-04) North Sindh Urban Services Corporation (NSUSC)

Water Supply System Mapping for six towns in Northern Sindh Water Supply Master Plans Water Management Master Plans Solid Waste Management Master Plans Detailed Engineering Designs and Technical Specifications Sewerage and Drainage Design Environmental Safeguards Documentation Social Safeguard Documentation Preparation of Procurement Documents and Evaluation of Proposals Construction Supervision, Project Management and Quality Control Feasibility Studies and Preliminary Design of Sub-Projects Land Acquisition, Resettlement and Social Assessments Asbestos Management

2013
Feasibility Study & Detailed Design of Up gradation of Rawal Lake Filtration Plant Rawalpindi WADA

Water and Sanitation Agency Rawalpindi awarded M M Pakistan the contract for Consultancy Services for “Feasibility Study & Detailed Design of Upgradation of Rawal Lake Filtration Plant Rawalpindi”. The contract was signed on 5th of January 2012, with a three months time to complete the study. The consultant is required to identify for Upgradation of water treatment plant compatible to treat the raw water of Rawal Lake.

2012
Implementation Assist and Consultancy Services for National Programme for Improvement of Watercourses in Sindh – Mirpurkhas Region Agriculture Department Government of Sindh

Assistance in survey, design work and authentication of cost estimates of watercourses. Supervision of construction work. Assurance of quality as per specified standards and designs. Technical assistance and overall coordination of project implementation. Assistance in social mobilization, mass mobilization and awareness campaigns. Organize seminars and workshops for the mass mobilization and awareness campaign. Preparation of the database for the works carried out in the project.

2012
Implementation Assistance and Consultancy Services for National Programme for Improvement of Watercourses in Sindh – Hyderabad Agriculture Department Government of Sindh

Assistance in survey, design work and authentication of cost estimates of watercourses. Supervision of construction work. Assurance of quality as per specified standards and designs. Technical assistance and overall coordination of project implementation. Assistance in social mobilization, mass mobilization and awareness campaigns. Organize seminars and workshops for the mass mobilization and awareness campaign. Preparation of the database for the works carried out in the project.

2012
Feasibility Study to Divert the Municipal Sewage and the Industrial Effluents Entering the Canal and River System of Peshawar Valley Executive Engineer, Peshawar Canals Division, Irrigation and Power Department, Khyber Pakhtunkhwa

The Project relates to the mitigation of effluent and solid waste disposal into the canal system of Peshawar Valley. It covers both the Peshawar and Mardan canal circles for a total of seven major irrigation channels. The consultancy service oversees a baseline evaluation of the problem through surveys and mapping, qualitative and quantitative estimation of the wastes through sampling and engineering interventions to divert the pollutants for treatment and safe disposal. The Project concludes with a feasibility report and PC-I to estimate costs for the interventions recommended across the system, including construction of STPs at various locations.

2012
Environmental and Social Due Diligence for LNG Terminal Overseas Private Investment Corporation (OPIC), USA

Meet with the relevant regulators, especially those that are involved with approving the project, giving permits etc. Meet with the affected and nearby communities, solicit first hand views from community members. Review project’s hazard assessment studies in view of the project settings and determine the adequacy of project’s safety measures. Assess the impacts on fishermen and other project affectees, assess the adequacy of project’s compensation plan. Assess impacts on indigenous people, document, if possible presence or absence of indigenous people. Review project site and the nearby areas for any environmental and social issues that the ESIA has not addressed or issues that are not included in the above points.

2012
Solid Waste Management Project in Faisalabad, Punjab on Public Private Partnership Modality IPDF, Urban Unit, Government of Punjab

Review of the relevant information Review of the technical aspects of the existing system Gap analysis Case study of NGO (Gold Green) involved in SWM Time and motion study Design parameters

2010
Sindh Basic Urban Services Project Government of Sindh

Sectoral review, policy and institutional analysis, lessons learned, urban centre selection, detailed poverty assessment, data collection on infrastructure and municipal services delivery. Project planning and design through consultations with stakeholders to reach consensus. Detailed feasibility studies and project design, including project costs, financial and economic analysis, social and resettlement assessment, environmental assessment, capacity building and institutional strengthening and implementation arrangements.

2006
Karachi Water Supply Improvement Project (KWSIP) OCEF / KWSB

Preconstruction stage: Review prev. reports on Hub Treatment Plants and firm-up recommendation; Review preliminary design report on Manghopir Pump Station; Finalise Project. Detailed Design, Geotechnical Investigation, Implementation Programme; Assist Evaluation of Bids. Construction supervision Stage: Provide supervision services; approval of plant design; Provide specialist service; Finalise O&M manual; Supervise operator training programme; Visit to manufacturers. Strengthening KWSB's capabilities commissioning and operation reporting on design completion.

2006
Consultancy Services for Design of Civil Works of Water Supply Schemes in Earthquake Effected Areas of AJK and NWFP UNICEF, Islamabad

Damages to the Civil Works to water supply schemes in all the 5 districts of effected areas were assessed and assessment report was sent to UNICEF. Damaged Civil Structures to be re-constructed or repair/rehabilitated was designed. Market Surveys were carried out of the area to ascertain the market rates of items and labour. The rates of items of constructions were analysed on the market rates. Estimates were prepared for all the works to be done. B.O.Q were prepared for all the works to be done. Tender conditions, agreement and technical specifications were prepared for all the works to be done.

2006
Feasibility Study for Construction of two lane Highway from Hyderabad-Khokhrapar National Highway Authority

Feasibility study and Survey work related to the Hyderabad-Khokhrapar. Proposed alignment of the road. Reconnaissance Survey Geotechnical investigation Topographic Survey Traffic Count Study Proposed Design of Hydraulic and irrigation structures as per site requirements. Draft Feasibility Report Final Feasibility Report

2006
Fact Finding & Recommendation Study on Water Supply and Sewerage System in Karachi Japan International Cooperation Agency (JICA) JICA in respond to Pakistan Government’s request to Government of Japan for technical cooperation has decided to undertake Development Study for Karachi Water and Sewerage Master Plan. Towards preparation for a comprehensive study for master planning a preliminary data collection and situation analysis study. Main goal of this Fact Finding Study is to collect and analyse the data and information to improve the present condition of water supply and sewerage service in Karachi. In order to bring those improve the present condition of water and sewerage service in Karachi. In order to bring those improvements, this study analyses existing system including socio-economic, environmental condition and the KWSB’s institutional and financial situation. Special attention to water scarcity and sewerage overflows in slump areas (Katchi Abadis) shall be paid on the humanitarian grounds. Key findings of the study will encompass the plan and strategy of further project activities 2017
Urban Water Supply and Sanitation Project, Rawalpindi ADB

Rehabilitation and improvement of rawal lake treatment plant; rehabilitation on conductance main construction of new conductance main rehabilitation of existing tubewells; installation of new tubewells; installation of meters, rehabilitation of priority areas sewerage system, hydrogeological study, Rawalpindi lake catchment study, master plan for sewage and drainage, preparation of development package of next phase.

2003
Punjab Private Sector Groundwater Development Project World Bank

The project cover the impact evaluation of drainage tubewells in Punjab Private Sector Groundwater comprising mainly of Physical aspects, impact on cropping pattern, change in land use, water course improvement, impact of canal lining, sociological aspects on financial viability, small farmers, community participation and economic aspects.

2010
PDOHA-Bulk Water Supply Project (New Pumping Main) DHA, Karachi

The scope of services included the study of various alternatives for protection of existing main, selection of suitable alternative, field investigations, evaluation of existing bulk water supply system, detailed engineering design of the new pipeline, design of inter-connection pipe, preparation of Tender Documents, BoQs, Cost Estimates, recommendation on implementation arrangements, Pre-bid services, contract management and construction supervision

2003
Health, Safety & Environmental Audit (HSE) for Oil & Gas Assets in Pakistan Govt. of Pakistan

Privatization Commission of Pakistan wished to sell working interests in nine (9) Oil & Gas concessions, which were in Badin, Upper Indus and Sindh Province. Orient Petroleum Inc. of USA, a prospective buyer, awarded Contract to Mott MacDonald (UK) to carry out HSE Audit of these sites. Mott MacDonald appointed MM Pakistan to undertake this Audit.

2002
Initial Environmental Examination of the White Oil Pipeline of PARCO PARCO

Baseline study and IEE were conducted for the new white oil pipeline to be laid from Port Qasim, Karachi to Mehmood Kot’s Mid Country Oil Refinery. The pipeline is 813 Km long may pass through sensitive areas.

2000
Soil and Groundwater Assessment of Depots/Installations/ Airfields Shell Pakistan Limited

Soil and Groundwater Assessment of Environmental damage due to oil pollution were made and remedial measures were suggested for Depots / installations / airfields of Shell Pakistan, scattered throughout the country.

2000
Hydro-geological Survey for Additional ground-water development at Engro Plan - Daharki, Sindh Engro chemicals The project included Survey to develop a site map Design VES Program & supervise execution Design & supervise test boreholes Design new boreholes 1999
Sindh Rural Water Supply and Sanitation Project Public Health Engineering Department

Provision of technical assistance to strengthen PHED, Sindh through training and the development of a participatory approach to the implementation of rural water supplies.

1999
Malir Bulk Water Supply Govt. of Sindh Collection of data and information study existing sources. Preparation of feasible independent bulk water supply system for MDA area after investigation various alternate sources e.g. Indus, Hub, Groundwater, Dumlottee Wells and desalination. Environment Impact of suggested alternate, PC-I, Financing Plan. 1999
Study for the Integrated Development of North East Swat Govt. of NWFP Study to develop a master plan for rural development including roads, irrigation, water supply, agriculture and social facilities. 1998
Lower Indus R.B. Irrigation and Drainage Project (RBOD) Govt. of Sindh Construction supervision. MMP provided one ARE on RBOD extension for 24 man-months one Senior Engineer on MRV Drain for 30 man-months and one Senior Engineer on Rato Dero for 27 man-months. 1998
Impact Evaluation of Second Scarp Transition Project (SSTP), Punjab World Bank/ Govt. of Punjab Impact evaluation of the SSTP involving long term monitoring of groundwater levels and salinity and evaluation to determine the effect of tubewell privatisation. 1998
Waste Minimization and Cost Effective Treatment - Seminar British Council - WWF A 2-day training course conducted on waste minimization and cost effectiveness treatment in Lahore. 1998
Environmental Baseline Studies, Kirthar Range, Dadu, Sindh LASMO Environmental baseline study of proposed oil and gas exploration and production concession area. Involved surveys of land, water, soil and agricultural resources. Feasibility study. 1998
Socio-Economic Study for Korangi Sewerage and Wastewater Management Project KW&SB, Govt. of Sindh The field study was conducted to formulate alternative livelihood package for agricultural workers who might be affected by the project. Also, Social survey of Korangi and Landhi townships were conducted to assess the willingness to pay for improved sanitation facilities 1998
Preparation of Lahore Solid Waste Management Plan through PSP Lease Pak (Pvt) Ltd., Lahore MCL intended to enter into a performance contract with a Private Sector firm for the Lahore Solid Waste Management, including waste collection, street sweeping, drains cleaning, composting and landfilling as well as incineration for a period of 5 years. A comprehensive proposal was prepared for solid waste management of Lahore city including collection and recycling and disposal. Prepared plan for Lahore city for a zonal collection of solid waste management system on daily basis. 1998
Parco Mid Country Oil Refinery EIA Project Stork Engineers and Contractors B.V. Factual report on applicable law and policies, factual report on available data on environment quality and development within range of 15 Km. Attend to comments by Client, write comprehensive EIA, chapter and survey provide guidance to client's team during its visit to Pakistan, advise SE&C on specific questions. 1997
ECF - Post Flood Rehabilitation and Protection Project European Community Production of 20 Tax Report Assist PMU of Development projects in Asia which receive assistance from European Commission, aimed at strengthening local ownership of these projects and fostering a democratic transparent and accountable environment. 1997
ICI - PTA Plant Water Supply Main - Port Qasim ICI Construction Supervision of a 51 Km Water Supply Pipeline at Port Qasim. 1997
D.G. Khan Rural Area Development Project ADB Rural Area Development: Social aspects; Irrigation Engineering; Watershed Management; Livestock; Rural Roads; Environmental Aspects. 1997
Lahore Urban Drainage Construction Supervision Consultancy WASA, Govt. of Punjab Construction management, supervision quality control, certification of work. Monthly reporting on overall progress, contractors resources, details of material at site and status of payment. 1997
Strengthening of Environmental Management for Water Resources Projects (WAPDA) ADB/WAPDA Institutional strengthening of the WAPDA environmental cell. Environmental and GIS training and the development approaches to environmental assessment. 1996
Water Loss Reduction World Bank Preparation of CAP TAL works programme for distribution system improvement. River institutional strengthening plan. 1996
Leak Detection Study KDA Evaluated the potential to reduce leakage by developing and active leakage control policy. The main feature was pilot test area on which the economic benefits of different methods of control were assessed. Training was a major component of the project covering all aspects required to develop, establish and maintain a leakage control policy. 1994
Environmental Study for Lahore Ring Road, Punjab World Bank/ LDA Assessment of the environmental impact of the proposed Lahore Ring Road to deflect external and cross city traffic away from the areas of the city. 1993
Pakistan Sectoral Environment Assessment (National Drainage Programme) World Bank Nationwide examination of environmental issues (water quality, health, wildlife) related to existing land drainage practice; identification of developments in drainage and corresponding measures to avoid adverse environmental impact. Study and training. 1992
Solid Waste Management Studies of Towns of Central Cluster of Province of Sindh Brisbane City Enterprises Pvt. Ltd. Under Sindh Cities Improvement Program (SCIP)
  • Solid waste generation study including household, commercial, industrial and hospital waste.
  • Solid waste composition study providing necessary inputs for calculating organic and inorganic portions, recyclable materials and combustible waste etc.
  • Data acquisition for time and motion study to find out existing fleet of vehicles, locations of official primary collection points to the existing dumping sites.
  • Also carry out time and motion study for each vehicle which is presently involved in the transportation of solid waste from official primary collection points to the existing dumping sites by giving details of routes and time take for one day.
  • Inventory of existing solid waste management physical infrastructure including assets and staff deployed by the towns, as well as all officially designated and non-designated primary collection points.
2013
Feasibility Study to Divert the Municipal Sewage and the Industrial Effluents Entering the Canal and River System of Peshawar Valley Executive Engineer, Peshawar Canals Division, Irrigation and Power Department, Khyber Pakhtunkhwa

The Project relates to the mitigation of effluent and solid waste disposal into the canal system of Peshawar Valley.  It covers both the Peshawar and Mardan canal circles for a total of seven major irrigation channels.  The consultancy service oversees a baseline evaluation of the problem through surveys and mapping, qualitative and quantitative estimation of the wastes through sampling and engineering interventions to divert the pollutants for treatment and safe disposal.  The Project concludes with a feasibility report and PC-I to estimate costs for the interventions recommended across the system, including construction of STPs at various locations.

2012
ECF - Post Flood Rehabilitation and Protection Project European Community

Production of 20 Tax Report Assist PMU of Development projects in Asia which receive assistance from European Commission, aimed at strengthening local ownership of these projects and fostering a democratic transparent and accountable environment.

1997
Disaster & Climate Resilience Improvement Project

This project aims to strengthen the existing flood infrastructure and make it more resilient to cope with the changed climate effects on river flooding. The Punjab Irrigation Department has contracted MMP, which leads an association comprising MML and Techno Consult International, to provide the following services: topo-surveys; environmental and social mitigation plans; design of existing infrastructure and construction supervision of civil works with sole responsibility of “The Engineer” on behalf of the client.

2019
Monitoring & Evaluation of Punjab Agriculture Productivity Improvement Project (PIPIP) Agriculture Department, Government of Punjab

MMP, as the lead firm in association with MML, Associated Consulting Engineering (ACE), and Temelsu, is providing the following services on this 5-year assignment:

  1. Monitor the physical progress of project activities, including High Efficiency Irrigation systems, improvement of watercourses and precision land levelling;
  2. Develop project monitoring information system;
  3. Conduct impact assessment studies; and
  4. Conduct overall project evaluation.
2018
Preparation of Master Plan for Water Supply, Sewerage and Drainage System for Lahore WASA LDA

WASA Lahore has engaged a consortium of consultants led by MMP, including MML and JERS to prepare the Master Plan with a 25-year planning horizon and identification / prioritisation of the project. This includes provision of physical infrastructure including water supply, sewerage, storm water drainage and waste water treatment with detailed designing and costing or the Lahore District to meet the present and future requirements for efficient and effective service delivery.

Our consultants are also assessing the existing infrastructure and proposing rehabilitation and expansion, including reviewing the regularity framework. We are also reviewing the tariff structure and introducing a sound financial management system based on MIS.

2019
Hydrological & Geotechnical Studies, Channelisation of Nullah and Design Review of Structure in Thor Colony – Bhasha Dam

The Thor Colony is located in Thora Valley, almost 15kms upstream of Diamer Bhasha Dam. The main objective of the assignment is to protect the Thor Colony against floods, flow of boulders and rolling stones in the tributaries of the Thor Nullah, as well as the upgradation of existing structures, including a 3.6MW power project.

Other services being provided include data collection, surveys, hydrological and geological studies, review of existing structures, detailed design of structures to protect the colony from floods and landslides, PC-1, and cost analysis.

Project Implementation Consultancy Services for Sindh Water Sector Improvement Project

On this 8-year assignment, Sindh Irrigation and Drainage Authority (SIDA), contracted the consortium of MML, MMP and BM Consulting Engineers to provide assistance and support to SIDA and AWBs for institutional reforms. The project’s main objective is to improve and rehabilitate the irrigation system in Ghotki, Nara and Left Bank AWB. Key services on this assignment include: institutional reforms; condition, topographic, geological and other surveys; prioritising and ranking and planning rehabilitation works; detailed designs; cost estimates, benefits, and economic analysis; tender documents; environmental assessment and environmental management plan; social impact assessment and resettlement action plan; water accounting and management system; trainings; procurement of goods and works; contract management and contract supervision; and capacity building.

Consultancy Services for Construction of Surface Water Treatment Plant of 100 Cusecs from BRBD Canal upstream of Ravi Syphon, Lahore Water and Sanitation Agency (WASA), Lahore
  1. Construction of 100 Cusecs (54 MGD) Surface Water Treatment Plant (SWTP) i.e. Intake Structure at Escape Channel of BRBD Canal, Pre-Sedimentation Tanks, Flocculation and Clarification Chambers, Clarifiers, Rapid Gravity Filter Beds, Clear Water Tank, Ground Storage Tank, Chlorination Room, Admin Building, Residential Building and Internal Roads etc.
  2. Providing and laying of Transmission Main of 60” Dia. Ductile Iron pipe from SWTP to the Underground Tanks of the 04 Serving Areas.
  3. Construction of 04 No. Underground Tanks, Rising Mains and 23 No. Overhead Reservoirs.
  4. Providing and Laying of Distribution Network of HDPE Pipes and 100% Water metering in the 04 Serving Areas.
2019